1 |
Provision of Basic and Detailed Engineering,
Procurement, Construction and Commissioning (BEPCC) Package
for Rejuvenation of Urea Ship Loading Facilities Project at
ASEAN Bintulu Fertilizer Plant, Bintulu, Sarawak (DABAI) |
Jun 2017 - Jan 2019 |
ASEAN Bintulu Fertilizer Sdn. Bhd. |
Total replacement of reclaiming scrapper (BUS1), tripper
car (BUS1), screening station parts, transfer station
parts, partial replacement of conveyor system, total
replacement of ship loader and partial replacement of
compact & jetty Substation. |
2 |
Provision EPCIC of LCOT Effluent Discharge Pipeline
Replacement Project – Onshore Section |
2016 - 2019 |
SABAH SHELL Petroleum Company/ SARAWAK SHELL Bhd./ SEA
HIBISCUS Sdn. Bhd. |
Detailed design for procurement, construction,
installation and commissioning engineering
Procurement and supply including transportation of
permanent Items i.e. HDPE pipe, metering station &
etc.
Construction & installation – site preparation,
civil works (sump pit), onshore HDPE pipeline
installation, perform leak test (0.875MPa)
Decommissioning and removal
Commissioning & system performance test
|
3 |
Procurement, Construction & Commissioning of
Underground Pressurized - Non-Metallic Piping Fire water
Network East Side |
Aug 2016 - Nov 2019 |
PRPC Utilities & Facilities Sdn. Bhd. |
Installation of various sizes of GRE pipeline for RAPID
Project fire water system. |
4 |
Provision of Repair and Maintenance of Sabah Sarawak Gas
Pipeline (including extension) |
Dec 2015 - Dec 2019 |
PETRONAS Gas Berhad/ SMSO |
Provision of material and manpower resources for the
repair and maintenance works which covers the following:
Pipeline repair and rehabilitation coating repair,
composite reinforcement sleeve, mechanical clamp, epoxy
filled sleeve, pipe cut out/ replacement & hot tapping
Civil works and ROW maintenance soil investigation,
pipeline alignment and site survey, buoyancy control, ROW
and facilities maintenance & system start-up
Work order - slope repair & exposed pipeline
rectifications (15 locations of Geo-hazard repair)
Work order - pipeline sectional replacement (1 location
of mechanical repair)
|
5 |
Engineering, Procurement, Construction and Commissioning
(EPCC) of New Export Terminal Scrapper Station (NETTS) |
Nov 2015 - Dec 2016 |
PETRONAS Gas Berhad |
Installation of the new scraper station for propane and
butane pipelines at Teluk Kalong, Kemaman to replace the
Tanjung Sulong Export Terminal (TSET) scraper station |
6 |
Engineering, Procurement, Construction and Commissioning
of Fire Sprinkler System Upgrading at Pasir Gudang LPG
Terminal. |
Sep 2014 - Mar 2015 |
PETRONAS Gas Berhad |
Design, supply, install, test and commission four units
of 6 inch deluge valve, one unit of 4 inch deluge valve,
two (2) units of 3 inch deluge valve c/w fitting,
accessories, necessary modification and associated works.
Installation of new piping for pilot line. |
7 |
Procurement, Construction and Commissioning (PCC) of
Pangerang Gas Pipeline Project (Formerly Known as
Procurement, Construction and Commissioning (PCC) of RGT2P
Pipeline Project) |
Apr 2014 - Jun 2016 |
PETRONAS Gas Berhad |
Installation of 36” x 73km onshore gas pipeline system
inclusive of launcher and receiver station, block-valve
station (3 nos.), HDD - Highway crossing, HDD River
crossing and push-pull River crossing (1.8km) SCADA and
PLDS and a gas metering station. |
8 |
EPCC OF PRAI II LATERAL GAS PIPELINE PROJECT
Engineering, Procurement, Construction, Commissioning
(EPCC) for the 22km NPS28 pipeline from Lunas to PRAI |
Sep 2013 - Dec 2014 |
PETRONAS Gas Berhad |
Installation of 28” x 22km onshore gas pipeline system
including a new meter station at PRAI, and associated
pipeline facilities (launcher/ receiver station and gas
metering station) as well as block valves, cathodic
protection and SCADA. |
9 |
The Engineering, Procurement, Construction and
Commissioning (PCC) of Biodiesel (B5) Storage & Blending
Facilities and its Associated Accessories at PDB Fuel
Terminals in East Malaysia |
May 2014 - Sep 2014 |
PETRONAS Dagangan Berhad |
To procure, supply, fabricate, install, construct,
inspect, test and commissioning, biodiesel (B5) facilities
which comprises of offloading system facilities, storage
tanks facilities and delivery system facilities. |
10 |
Provision of EVA-NMB Gas Delivery System (ENGDS) Shore
Approach for PCSB Project – Onshore Section |
2013 |
PETRONAS Carigali Sdn Bhd/ Global Offshore Malaysia
Resources Sdn. Bhd. |
Engineering support design and analysis
Pre-installation and post installation survey
Loading, securing and inland transportation of pipeline
and associated components.
Pipeline installation (aboveground and underground)
Installation project materials (permanent flange, MIJ,
etc.)
|
11 |
LEKAS Regasification (RGI- 1) Project |
Jul 2012 - Jul 2013 |
PETRONAS Dagangan Berhad/ IGS Subsea |
Cleaning, pneumatic strength testing, inserting, leak
testing and flange management of cryogenic piping system. |
12 |
Provision of 14” and 24” Export Pipeline Shore Approach
Installation for KEBABANGAN Northern Hub Development |
2011 |
KEBABANGAN Petroleum Operating Company/ Global Offshore
Malaysia Resources Sdn. Bhd. |
Provision of installation engineering & deliverables
Onshore pipeline construction and installation
|
13 |
Transportation and Installation of Offshore Facilities
for Year 2004 – 2006 (Extension) - Provision of Shore
Approach Pipeline Installation for 28” dia from KAKG-A to
MLNG2 |
2010 |
PETRONAS Carigali Sdn. Bhd./ TL Offshore Sdn Bhd |
Provision of installation engineering & deliverables
Onshore pipeline construction and installation
|
14 |
EPCC of the Upgrading of Fuel Oil Bunkering Facilities
at Bintulu, Sarawak for PDB |
Jan 2009 - Jan 2010 |
PETRONAS Dagangan Berhad |
Installation of 16”x5km multi-product transfer pipeline,
bunkering and export facilities from MLNG to Bintulu export
terminal. Work includes custody transfer metering,
installation of process pumps, upgrading of process piping
as well as electrical and instrument system. |
15 |
Procurement, Construction and Commissioning (PCC2) LGAST
to PML-2 Pipeline Project |
Nov 2006 - Mar 2007 |
PETRONAS Carigali Sdn Bhd/ PETRONAS Methanol |
Construction/installation of onshore pipeline and
appurtenances
12” dia. x 10.649km LGAST to PML-1 pipeline
8” dia. x 708m PML-1/ PML-2 pipeline
6” dia. x 708m pipeline PML-1/ PML-2
|